Aventura, Florida · serving clients across the United States (305) 404-9404Toll-free (800) 767-8566Emergency? Get a call within 1 hour
Technology, datacenter and colocation infrastructure Illustrative engagement

Two colocation sites from empty cages: 40 racks, GPU, storage and compute, built, burned in and handed over

A fast-growing fintech and AI company in the United States, a leader in its segment.

Scale
2 colocation sites, 20 racks each, about 300 kW of IT load per site, A/B power, 400G spine, 100G and 25G leaf, 200 servers burned in, about 2,000 labeled cables per site
Engagement
About nine months from first site visit to the second site's acceptance; each site took a 16-week build

The challenge

The company's cloud bill for steady-state compute, storage and GPU training had outgrown its value, and latency-sensitive systems needed a home next to their counterparties. It wanted two owned footprints in different metros, built from empty cages, running the same design, without hiring a facilities team. Deadlines were fixed by a cloud commitment that ended and by hardware delivery dates.

The company ran a growing share of its work in the public cloud: steady databases, a training cluster and trading-adjacent services that needed to sit near their counterparties. The cloud bill for work that never changed shape had passed the cost of owning it, and a commitment was about to end. The plan was two owned footprints in different metros, each built from an empty cage and running the same design, and without hiring a facilities team, so our team took the build from the first site visit to handover. The site survey came first. We visited five candidate facilities and scored them on what the sales sheet leaves out: the power each cabinet can really draw, whether the electrical and cooling paths are redundant all the way to the cage, which carriers are in the building, what cross-connects cost and how long they take, who may enter and when, and how the building fares in a flood or a hurricane. Two facilities won, and we read each contract for expansion rights, because a cage that cannot grow becomes a second project.

The design started with a rack elevation for each type. Each site has 20 racks in cold-aisle containment: 7 GPU racks, 4 compute racks, 4 storage racks, 2 network racks and 3 racks for operations and growth, for roughly 300 kW of IT load. Typical draw guided the layout: storage 5 to 8 kW per rack, general compute 10 to 15 kW, and GPU racks 20 to 40 kW. An 8‑GPU training node draws around 10 kW, so a GPU rack holds three and needs rear-door heat exchangers, which we agreed with each facility before ordering. Heavy servers go low, switches sit in fixed positions, and a blanking panel fills every empty unit so air cannot recirculate. Inlet air stays inside the ASHRAE recommended band of 18 to 27 degrees C.

Power was designed in pairs. Every server's two power supplies go to an A and a B feed from separate paths, through metered three-phase PDUs, and each feed must carry the whole rack if the other fails. A 32 A, 400 V three-phase feed is 22.2 kVA, and loaded to 80% it gives 17.7 kW usable per A/B pair, which suits compute and storage racks. GPU racks use 63 A feeds. The network is a spine-leaf fabric: 400G spine links, 100G uplinks to storage and GPU servers, 25G to compute, BGP with EVPN-VXLAN, and two 100G waves between the sites for replication. Short runs use direct-attach copper, rack-to-rack runs use active optical cables or 100GBASE-SR4 over OM4, and room and inter-site uplinks use OS2 single-mode.

Cabling and servers were built in the same weeks. Each site followed a 16‑week plan: survey and design in the first four weeks, procurement as the longest phase because switch, GPU and optic lead times set the pace, racking and cabling overlapping, then burn-in, acceptance and a scheduled cutover. We fixed MPO-12 trunks between the network racks and each row, ended them in patch panels, checked polarity with a tester before any switch was connected, and routed Cat6A for management in its own managers. Every cable and port carries a label to the TIA-606 scheme, so about 2,000 cables per site can be traced from either end. Our team assembled 200 servers across the two sites, pinned firmware to one baseline per model, configured BMCs for Redfish and IPMI, and burned each one in for 48 to 72 hours with memory pattern tests, CPU and GPU stress, NVMe write and verify, and line-rate network tests. Burn-in found 21 faulty parts out of thousands: 7 DIMMs, 1 CPU, 4 GPUs and 9 NVMe drives, all replaced under warranty before any workload arrived.

Acceptance was a written checklist, not a feeling. We pulled each A feed and each B feed in turn and confirmed that nothing dropped, failed a link on every spine, cut the primary uplink to prove the out-of-band path and watched inlet temperatures during a deliberate reduction in cooling. Only then did workloads arrive, in waves, each behind a method of procedure with a rollback. The DCIM records every device, rack unit, port, cable and outlet, and a change is not closed until the record matches the room. Handover decides whether the build lasts: the company's own team received the elevations, power budgets, cable schedules, runbooks and the baseline firmware set, and a remote-hands contract covers drive swaps and re-seating when nobody is on site. Decommissioned gear leaves under a media-sanitization procedure based on NIST SP 800-88. This case is illustrative: the power, rack, server and failure figures are modeled for a build of this kind. Our guide to optics from 10 to 400 Gb/s and our article on separating networks across datacenters explain the network choices.

What our team delivered

  • Site survey of five candidate facilities, scored on power per cabinet, electrical and cooling redundancy, carrier choice, cross-connect terms, access rules and flood and hurricane exposure, narrowed to two
  • Cage design with 20 racks per site in a cold-aisle containment layout: 7 GPU racks, 4 compute racks, 4 storage racks, 2 network racks and 3 racks for operations and growth, with one rack elevation drawn and reviewed per type
  • Power from A and B feeds on separate paths and metered three-phase PDUs: 32 A, 400 V feeds (17.7 kW usable per pair at 80% loading) for compute and storage racks, 63 A feeds for GPU racks, and rear-door heat exchangers agreed with each facility
  • A spine-leaf fabric with 400G spine links, 100G uplinks to storage and GPU servers and 25G to compute, BGP with EVPN-VXLAN, and two 100G waves between the sites for replication
  • Structured cabling to TIA-568: Cat6A for management, OM4 with MPO-12 trunks for parallel 100G inside the room, OS2 for uplinks and the inter-site links, fixed trunks to patch panels, every cable and port labeled to TIA-606
  • 200 servers across both sites built by our team (about 40 eight-GPU training nodes, 100 dual-socket compute servers with DDR5 registered memory and NVMe, 60 NVMe storage nodes), firmware pinned to one baseline per model, BMCs configured for Redfish and IPMI
  • A 48 to 72 hour burn-in of every server (memory patterns, CPU and GPU stress, NVMe write and verify, line-rate network tests) that caught 21 faulty parts, all replaced under warranty before go-live
  • An out-of-band network with console servers and a separate carrier uplink at each site, a DCIM recording every device, rack unit, port, cable and outlet, method-of-procedure change windows for each cutover wave, and acceptance tests including a feed pull and a cooling-degradation test

Result

Both sites were accepted against a written checklist, production workloads moved over in waves with a rollback ready for each, and the company's own staff operate the rooms with our documentation and a remote-hands contract. Power, rack, server and failure figures are modeled for a build of this kind, not measurements from a client.

A colo cage seen from above

Racks face each other across a contained cold aisle and exhaust into hot aisles that return to the cooling units. Two rows of busway carry A and B power from separate UPS systems, and fiber and copper run overhead on a ladder rack from the meet-me room.

A colo cage seen from aboveA top-down plan of a colocation cage with two rows of six racks. Their fronts face each other across a cold aisle that is enclosed with end doors and a roof. The rears face outer hot aisles. Cold air moves from the aisle into the rack fronts, hot air leaves the rears and returns to two CRAH cooling units at the right. Two UPS systems, A and B, feed two busways above each row, and every rack takes one whip from each, so a single UPS or busway can fail without an outage. An overhead ladder rack runs along the cold aisle carrying fiber and copper from the meet-me room, where cross-connects join the cage to carriers, and drops to each rack. A1B1A2B2A3B3A4B4A5B5A6B6UPS APDU AUPS BPDU BCRAHhot aisle returnCRAHhot aisle returnMeet-me roomcross-connectscold aisle · containedhot aislehot aislecold airhot airfibercopperpower A (solid)power B (dashed)A and B from separate UPScross-connects in the meet-me roomladder rack overhead

A 42U rack, racked in build order

Heavy gear goes in at the bottom, switches and patching at the top, with cable managers and blanking panels in between. Vertical A and B PDUs sit on opposite sides, and the animation shows the order the units are racked.

A 42U rack, racked in build orderA front elevation of a 19 inch 42U rack numbered from U1 at the bottom. U1 to U4 hold a 4U storage JBOD and U5 to U8 a 4U GPU server. Four 2U compute servers fill U9 to U16, eight 1U servers U17 to U24 and another 2U server U25 and U26. Blanking panels cover U27 to U37. At the top are a cable manager at U38, two top-of-rack switches with SFP28 and QSFP28 ports at U39 and U40, another cable manager at U41 and a 24-port patch panel at U42. Vertical power distribution units A and B run down opposite sides. A build-sequence list on the right highlights each step as the units appear in order: heavy gear, compute, network, cabling and power, blanking panels, then labelling and testing. ABPDU A, B: vertical, opposite sidesU1U10U20U30U40U42 patch panelU40-39 ToR A, BU41, U38 cable mgrsU37-27 blanking panelsU26-25 2U computeU24-17 1U computeU16-9 2U computeU8-5 4U GPU serverU4-1 4U JBODBUILD SEQUENCE1 Rack JBOD and GPU server2 Rack 2U compute3 Rack 1U compute4 Rack ToR, patch, managers5 Dress cables and power A/B6 Fit blanking panels7 Label, test, hand overToR: 48x SFP28 + 8x QSFP28GPU server: 8 GPUs, 4UJBOD: 4U, top-loading, SAS19 in rack · 1U = 44.45 mmA and B power feeds25G SFP28 · 100G QSFP28

A GPU server, taken apart and accepted

Two CPU sockets with eight DDR5 memory channels each, GPUs on SXM or PCIe, NVMe bays, a NIC with QSFP cages, a BMC speaking Redfish and redundant power supplies. Every machine then runs the same three gates: firmware baseline, burn-in, acceptance.

A GPU server, taken apart and acceptedAn exploded view of a dual-socket GPU server. At the centre is the motherboard with two CPU sockets joined by a socket interconnect and, beside each, a bank of eight DDR5 RDIMM slots, one per memory channel. Above it eight GPUs on an SXM or PCIe baseboard connect over PCIe Gen5. To the left are six NVMe bays for U.2 and E3.S drives. To the right are a network card with QSFP28 cages and a baseboard management controller with a Redfish API. Below it two hot-swap power supplies, A and B, feed the board. Along the bottom, three gates light in turn: firmware baseline, where BMC, BIOS and NIC firmware are set to a pinned version, burn-in, where CPUs, memory and GPUs are stressed, and acceptance, where every component shows a green check. GPUS · SXM OR PCIENVME BAYSU.2 and E3.SI/O AND BMCGPUGPUGPUGPUGPUGPUGPUGPUPCIe Gen5 x16 or NVLinkMOTHERBOARDCPU 1CPU 2socket link8 ch DDR58 ch DDR5NIC2x QSFP28 · 100GBMCRedfish APIPSU Ahot-swapPSU Bhot-swap1 Firmware baseline1 Firmware baseline2 Burn-in2 Burn-in3 Acceptance3 Acceptance16 DDR5 RDIMM · 8 channels per CPUGPUs: SXM or PCIe Gen5Redfish firmware control

A colo build in sixteen weeks

A typical colocation build from site survey to cutover: survey and design overlap, procurement runs longest because of equipment lead times, racking and cabling overlap, then burn-in, written acceptance and a scheduled cutover window. Illustrative schedule; lead times drive the real one.

A colo build in sixteen weeksGantt chart of eight colocation build phases over sixteen weeks. Site survey weeks 0 to 2. Design and bill of materials 1 to 4. Procurement 3 to 9. Rack and stack 9 to 11. Cabling and labelling 10 to 12.5. Burn-in 12 to 14. Acceptance 14 to 15. Cutover 15 to 16.Build phases by weekwk 0246810121416Site surveywk 0–2Design and BOMwk 1–4Procurementwk 3–9Rack and stackwk 9–11Cabling and labelswk 10–12.5Burn-inwk 12–14Acceptancewk 14–15Cutoverwk 15–16all racks poweredIllustrative plan. Lead times for switches, GPUs and optics are the usual critical path.

Frequently asked questions

Direct answers to the questions we hear most. Something else on your mind?

Send us a message
How was the colocation facility chosen?

Five candidate facilities were surveyed and scored on power per cabinet, electrical and cooling redundancy, carrier choice, cross-connect terms, access rules and flood and hurricane exposure, then narrowed to two.

How was power designed for each rack?

Every rack took A and B feeds on separate paths with metered three-phase PDUs: 32 A, 400 V feeds for compute and storage racks and 63 A feeds for GPU racks, with rear-door heat exchangers agreed with each facility.

What network connected the two sites?

A spine-leaf fabric with 400G spine links, 100G uplinks to storage and GPU servers and 25G to compute, BGP with EVPN-VXLAN, and two 100G waves between the sites for replication.

Who built and tested the servers?

Our team built the 200 servers across both sites and burned each one in before handover. Cabling followed TIA-568 and was labeled to TIA-606. Case figures are modeled for an engagement of this kind.